Description:
|
Pooltite® is
a premium, quality pool plaster available in a Pooltite Classic, Pooltite
White, Pooltite Blended and Pooltite® Pool Quartz composed
of white cement, selected quality aggregates and various admixtures
proportionately formulated for optimum product performance. It is
factory blended and packaged to provide a smooth durable finish for
swimming pools, spas, etc. |
|
Color:
|
White |
|
Preparation:
|
Pooltite® should
be applied to a sound surface free of oil, dirt, algae or any other
foreign substance. Previously applied paints or sealers must be removed
by acid washing and/or sandblasting. Neutralize acid with baking soda
or soda ash then thoroughly rinse with water. In addition to, or in
partial replacement of, the procedures mentioned above, CLI PermaKote®
could be used as a bonding coat. Re-finished pools must be undercut
an appropriate distance around all tile, return lines, light fixtures
and main drains. All weepers and plumbing leaks should be repaired
at least 24 hours prior to plaster application. |
|
Mixing:
|
1. Using
standard mixing equipment, it is important to blend each batch for
the same amount of time.
2. Mix Pooltite® with approximately 2 to 2 1/2 gallons of potable water
per 80-lb. bag.
3. Start the mixing procedure by adding approximately 2/3 of the total
water requirements to the mixer, and Pooltite® then add the balance
of water.
4. Mix the completed batch for at least 8 minutes to ensure a proper
blend of all ingredients.
5. Before using any job site additives, please consult your CLI Product
Service Representative at 800-333-2660. |
|
Application:
|
1.
Pooltite® may be applied by either spray or conventional
methods.
2. Apply Pooltite® over a lightly dampened (no standing
water) surface to a uniform thickness of approximately 3/8."
3. If application must be interrupted, finish to a natural break to
prevent joints from showing.
4. Substrate conditions will have a direct relationship on the thickness
of application and coverage rates per bag.
5. Pooltite® should be applied in temperatures exceeding
40†F.
6. The pool water must carefully balanced from the initial fill and
constantly maintained within recommended NSPI guidelines. Maintaining
proper chemical balance from first fill is essential to maximize the
life of the pool surface. Please consult your CLI Product Service
Representative concerning start-up techniques and maintenance programs. |
|
Filling
Procedures:
|
When
filling a pool it is important to do so without interruption of fill
water. Fill pool as rapidly as possible. All fill hoses should have
a sock or cloth on the end. Do not allow main hose length to lay on
the plaster surface, as it will leave a mark. |
|
Water
Chemistry:
|
The
pool water must be carefully balanced from the initial fill and constantly
maintained within recommended NSPI guidelines. Maintaining proper
chemical balance from first fill is essential to maximize the life
of the pool surface. Please consult your CLI Product Service Representative
concerning start-up techniques and maintenance programs. |